{"id":29902,"date":"2024-07-01T15:47:39","date_gmt":"2024-07-01T13:47:39","guid":{"rendered":"https:\/\/www.soletanche-bachy.com\/metro-de-toulouse-ou-en-est-on-de-lavancement-des-differents-lots\/"},"modified":"2025-01-21T17:10:50","modified_gmt":"2025-01-21T16:10:50","slug":"toulouse-metro-where-do-we-stand-with-the-progress-of-the-various-packages","status":"publish","type":"post","link":"https:\/\/www.soletanche-bachy.com\/en\/toulouse-metro-where-do-we-stand-with-the-progress-of-the-various-packages\/","title":{"rendered":"Toulouse metro: where do we stand with the progress of the various packages?"},"content":{"rendered":"
01\/07\/2024<\/p>\n<\/div>
Remember, the Cl\u00e9mence Isaure TBM began work 3 months ago, and the first section was completed on Wednesday May 15. As a reminder, two 260-meter-long tunnels with an internal diameter of 4.66 m will enable the Toulouse metro to cross the Canal du Midi.<\/p>\n
These underground structures make up lot 2 of the “Line B Connection”, linking the current terminus of line B with the future line C.<\/p>\n
The TBM will now be transported to the Ramonville structure to complete the second section. It will start its new run, parallel to that of the first tunnel, at the end of June, and should finish digging in September.<\/p>\n<\/div>